The intervention was performed to solve a major problem of infiltration and humidity on the wall of a bathroom in an apartment in the city of Cerignola (Foggia).

The preliminary video inspection carried out on the drainage column had shown a split along a double pipe in which the drainage pipes of the 2 bathrooms of the upstairs apartment were engaged.

Due to the complexity of the intervention the only non-invasive solution suitable to solve the problem was the relining by spraying high-performance epoxy resin – SPRAY COAT.

The intervention was executed in a few hours and by the afternoon the drains were usable again.

The final video inspection ensured the perfect rehabilitation and the total sealing of the damage.

 